F-building

To be completed in 2020, the F-building will house Clinical Nuclear Medicine and Haematology.

F-building in brief

  • Operations: Clinical Nuclear Medicine and Haematology
  • Location: On the Teiskontie side of the Central Hospital area, in the location of the former M-building
  • Schedule: The building is set for completion in May 2020, and operations are scheduled to begin in September 2020.
  • Total area: 9,154 gross square metres, treatment of patients on three floors
  • Contractor: TYL-F, i.e. work consortium Aki Hyrkkönen Oy and Alasen Rakennus Oy
  • Costs: Approx. €32 million

Person in charge

Construction Project Manager, Operation Manager Jarno Virolainen